Three workers can do a job in 28 hours. How many more workers are needed to do this job in 12 hours?

Respuesta :

MrRamon
MrRamon MrRamon
  • 13-04-2018
4 additional workers for 7 total workers.
if it takes 3 workers 28 hours to do work there are 84 total hours of work (3*28=84) to find how many workers it will take to get the work done in 12 hours divide 84 by 12. 84/12= 7 total workers. 7-3= 4 additional workers needed.
Answer Link
pranilraichura
pranilraichura pranilraichura
  • 08-03-2020

Answer:

4 workers

Step-by-step explanation:

Answer Link

Otras preguntas

What were some events/things that caused the Great Depression?
What is 0.05 percent of 6.5?
Can someone please help me ?
China, Korea, and Japan share cultural similarities in part due to their (1) clashes with Russian imperialists (2) shared river systems (3) contacts through tra
Why does Louis XIV want to expand France's border?
Why were people from Africa brought to Georgia?
USE A NUMBER LINE TO FIND 8/9 / 8/45.
A flight instructor charges $50 per lesson, plus an additional fee for the use of his plane. The charge for the use of the plane varies directly with the square
How many miles can you get on one tank of gas if your tank holds 18 gallons and you get 22 miles per gallon?
what does etymology study?