In a project network, the critical path is the sequence of activities which has the:________.

Respuesta :

66hello60
66hello60 66hello60
  • 03-08-2022

Answer:

The correct answer is the longest time

Answer Link

Otras preguntas

Petro Roos is thinking of purchasing the business premises rather than renting it. Provide Two separate advantages and two separate disadvantages of this option
In the first 30 seconds of the last video of the day, the narrator says, Big History...is a story of how we almost didn't happen." What does he mean by this?
If the problem says x=5 ,did it give you a input or output?
How did US labor unions treat Chinese immigrants in the 1800s? Labor unions discriminated against Chinese immigrants and did not allow them to join. Labor union
Show that |3| + |10| = |3| + |10| ​
What is the area of the trapezoid? 5 km 4 km 13 km 9 km
Provide an example using one organ for each of the four levels of complexity. Why is it difficult to make level four organs in a lab? Please help :)
Select the correct verb form to complete this sentence. Este fin de semana mis amigos y yo ______ al cine. ve vas vamos iremos
What did Robert Hooke look at under a microscope?
A button machine produces one button in 0.15 seconds. How many buttons are produced in 48.6 seconds?