if 25 worker need 3 days to build a house how long will 10 worker need

Respuesta :

sasukezwrldzxu
sasukezwrldzxu sasukezwrldzxu
  • 04-03-2021

Answer:

3 x 10 = 30 man-days per house

Answer Link
akbusiness987
akbusiness987 akbusiness987
  • 04-03-2021

Answer:

7.5 days

Step-by-step explanation:

Answer Link

Otras preguntas

write words to match the expression. 24- ( 6+3)
which city was located nearest the nile river delta
Which two numbers have a difference of 5 and a product of 3.36???
which city was located nearest the nile river delta
which city was located nearest the nile river delta
which city was located nearest the nile river delta
write words to match the expression. 24- ( 6+3)
which city was located nearest the nile river delta
write words to match the expression. 24- ( 6+3)
If you are writing a persuasive essay in favor of banning vending machines in schools, which is a counterargument you might anticipate?